  • Version Burnup report
  • Release Burnup report
  • Release Status report
  • Scope Change report
  • Board statistics report

Reports for Versions

Version Burnup Chart

...

  1. Period of the data aggregation. Te values are calculated by the formula: <# of items in period>= <# of items at the end of the period> - <# of items at the start of the period> +1 day 
  2. Scope change trend line.
  3. Velocity trend line.
  4. Scope change and velocity for the current period are outlined with a dotted line.

Reports for Releases

Release Burnup Chart

Release burnup chart is similar version burnup. It consists of two main parts:

  1. Cumulative scope. The chart shows the cumulative scope and progress for all the versions in the release on a daily base
  2. Separate charts for each version on the release. 

Image Added

Report logic is similar to versions burnup.

Release Trends Report

Info
titleScope

Will only take Fix Versions of specified release in account. For Virtual Versions we can't yet track history.

...

  1. Cumulative trends for all version in the release. 
  2. Separate trends for each version in the release. 

Release

...

Release burnup chart is similar version burnup. It consists of two main parts:

  1. Cumulative scope. The chart shows the cumulative scope and progress for all the versions in the release on a daily base
  2. Separate charts for each version on the release. 

Image Removed

Report logic is similar to versions burnup.

Release Status Report

Release status report helps users to understand the status of the release and all its versions.

...

User can select any release available in the Release Board using the Releases selector:


Release Milestones Reports

Release milestone report gives you an aggregated view on all milestones of cross-project release and its associated versions. 

To open the report choose "Milestones" in release section of "Switch report" drop down.

Image Removed

Choose one or several of your cross-project releases to generate the report.

Image Removed

How to read track bar?

Image Removed

  • Achieved states for milestones achieved at a date <= planned date
  • Achieved with delay states for milestones ticked as achieved at a date > planned date
  • On track means not yet achieved, but the planned date is in future (or empty)
  • Delayed means not yet achieved with planned date in the past

Adjustments and configuration

Image Removed

You can adjust the output by configuring some predefined filters:

  • Delayed will shortlist only delayed milestones, not delayed or ALL
  • Achieved will shortlist only achieved milestones, not achieved or ALL
  • By clicking on "Export to CSV" you can download the output

If you want to go into further details and see version specific milestones toggle "Show detailsat the bottom of the report.

Image Removed

Other Reports

Scope Change Report

...

  1. Statistics for all versions in the board
  2. Statistics for all releases in the board
  3. Number of versions or releases which were moved to a particular status during the selected period
  4. Transition detail button. It opens a pop-up with all transitions to the selected status.


    Info

    Transition details button is only available if 


  5. Export to CSV

Milestones Reports

Milestone report gives you an aggregated view on all milestones of cross-project release and its associated versions. 

To open the report choose "Milestones" in release section of "Switch report" drop down.

Image Added


Choose one or several of your cross-project releases and/or versions to generate the report.

Image Added

How to read track bar?

Image Added

  • Achieved states for milestones achieved at a date <= planned date
  • Achieved with delay states for milestones ticked as achieved at a date > planned date
  • On track means not yet achieved, but the planned date is in future (or empty)
  • Delayed means not yet achieved with planned date in the past

Adjustments and configuration

Image Added

You can adjust the output by configuring some predefined filters:

  • Delayed will shortlist only delayed milestones, not delayed or ALL
  • Achieved will shortlist only achieved milestones, not achieved or ALL
  • By clicking on "Export to CSV" you can download the output


If you want to go into further details and see version specific milestones toggle "Show detailsat the bottom of the report.

Image Added